Islamabad: The Federal Government has allocated Rs16 billion for 44 ongoing and new development projects in Karachi under Public Sector Development Programme (PSDP).
The Prime Minister’s Karachi package included five projects, with an estimated cost of Rs35.206 billion. So far, Rs25.837 billion has been spent while the remaining Rs9.369 billion is required for the timely completion.
The projects include:
- Reconstruction of Mangho Pir Road from Jam Chakro to Banaras Karachi
- Construction of flyover at Sakhi Hasan Five Star & KDA Roundabout along Sher Shah Suri Road Karachi
- Green Line Bus Rapid Transit System Karachi
- Reconstruction of Nishtar Road & Mangho Pir Road Karachi
- Rehabilitation of existing Fire Fighting System of KMC
Details of the allocated and incurred budget
Project Total Allocated Budget Incurred Budget
Green Line Bus Rs24.604 billion Rs21.166 billion
Greater Karachi Rs12.755 billion Rs9.598 billion
Water Supply Scheme
(K-IV)
Lyari Expressway Rs4.359 billion Rs4.310 billion
Combined Affluent Rs3.894 billion Rs500 million
Treatment Plant
(CETP)
M-9 Rs3.7 billion Rs.141 billion
Mangho Pir Road Rs2.440 billion Rs1.376 billion
Flyover Sakhi Hasan Rs2.380 billion Rs1.493 billion
Fire Fighting System Rs1.876 billion Rs1.021 billion
University of Karachi uplift Rs1.680 billion Rs75 million
Dawood University Rs579 million Rs445 million
Waste Water Treatment Plant Rs52 million Rs31 million
Karachi Expo Centre Rs2.677 billion Rs100 million