Islamabad: The Capital Development Authority (CDA) has expedited the expansion of dual carriageway Ataturk Avenue after issues with Islamabad Electric Supply Company (IESCO) are resolved, a CDA spokesperson told the media.
The project was started in 2017, but was suspended by the Environmental Protection Agency (EPA), as it involved cutting down of more than 100 trees.
After a go-ahead from EPA last year, the CDA resumed the development work, but soon ran into a dispute with IESCO. The later complained that IESCO laid electricity supply lines on CDA’s property without obtaining an NOC. IESCO maintained that since shifting of these service lines is required by CDA, it has to bear the cost.
When approached for a comment on the completion date of the project, CDA spokesperson Syed Safdar Ali said that no final date could be given for this project. However, since all issues are now being resolved, it will be completed without any further delay.
Rawalpindi: The Rawalpindi Development Authority has said that the long-awaited Rawalpindi Ring Road project is…
Here is a concise, professional rephrased version of the news: Saudi Arabia Approves Regulatory Sandbox…
Islamabad: Chairman of the Capital Development Authority (CDA), Muhammad Ali Randhawa, chaired a high-level meeting…
The 19th Real Estate Development Summit Saudi Arabia – Luxury Edition concluded after two days…
Islamabad: The Shaheen Chowk underpass is expected to be inaugurated next week after nearing completion,…
Dubai’s luxury real estate market has reached a new milestone in 2025, with a prime…