ISLAMABAD: The Islamabad Expressway projects, including PDW Underpass and Korang Bridge, will be concluded by the deadlines set for June 30 and December 31, the Capital Development Authority (CDA) ensured.
Since October, work on 40 out of 68 piles have been completed, whereas 16 out of 33 girders accomplished under the Korang Bridge project worth Rs650 million.
The authorities have also completed 70 per cent of work on the retaining walls.
The asphalt work is in progress on the east side ramps of the PWD Underpass, where the traffic will be diverted upon completion. The authorities have also completed shifting of utility services like IESCO and SNGPL.
The signal-free and U-turns-free road till project aimed at averting traffic jams will smooth out the flow for the daily commuters and residents living in housing societies along Islamabad Expressway and other adjoining areas.
For news and blogs, visit Graana.com.
Kalabagh, a small yet historically significant town in Pakistan’s Punjab province, is located within the…
Nazimabad Number 2 is a well-known neighbourhood in Karachi, Pakistan, renowned for its vibrant community,…
Quetta Town is a residential neighbourhood located in the vibrant city of Karachi, Pakistan. Known…
Akbar Chowk in Lahore stands as one of the city’s most critical intersections, serving as…
Khuda Baksh Colony, located near Bhatta Chowk in Lahore, is a rapidly developing residential area…
Gol Market in Karachi is one of the city's most iconic and bustling commercial centres.…